Certificate/Reg.-No. | 968/FSA 1193.00/19 |
Type of Certificate | FSA Certificate |
Certificate Holder | Emerson Process Management Chennai PTE Ltd. |
Product Category | Safety Instrumented Systems / SRECS / Safety Functions > HIPPS |
Subject | Design and engineering of R13A-HIPPS-SIF-R-13A related to ONGC R Series R-13A Well platform |
Type Designation | R13A-HIPPS-SIF-R-13A SIF Tag: SIF-R-13A |
Codes and Standards |
|
Scope and Result | FSA Stage 2 assessment within the scope of IEC 61511 SLC limited to Phase 4 for the Safety Instrumented System (incl. the IFAT): HIPPS of ONGC R Series R-13A Well platform. SIF: HIPPS is to close the shutoff valves on detection of high high pressure in the line. The assessment of the Certification Body came to the result that the documented design, engineering, fault avoidance and including validation activities comply with the requirements of IEC 61511 (Phase 4 of SLC) for SIL 3. Mode of operation: Low Demand Mode, Proof test interval: 1 year (full test); PFDavg = 7.66E-4 |
Specific Provisions | The project related safety manual(s) and the safety documentation delivered by the SIF element suppliers have to be considered. Any change in type of firmware of applied hardware and/or software modules and changes in the application logic requires a reassessment of the whole system. The validation of the above HIPPS regarding SAT is not covered by this assessment. |
Valid Until | no expiry date |
Appendixes | n/a |
Download Certificate | 968_FSA_1193_00_19_en_el.pdf |